Barry Island Causeway

McCarthys were employed by VOGC as a Principal Contractor for the challenging scheme.

A ramp up from the existing car park was constructed in the extremely soft marine deposits along with an armour stone revetment and tied into the existing delicate pitched revetment.

The Works

As part of a county wide scheme to improve cycle routes Harbour Road in Barry was modified.

Client Organisation Vale of Glamorgan Council
Contract Value Circa £360,000
Contract Period January to April 2016
Form of Contract/td> NEC3 Short Contract
Location Harbour road, Barry, CF62 5TQ