Isca Road Flood Alleviation & Ebbw Slip

Ebbw Slip

ISCA Road

Making tomorrow a better place

Value Engineering

Temporary roads were constructed from recycled materials

Sustainability

Temporary roads were constructed from recycled materials
Excavated material from river bank was remediated and utilised in flood bunds

Environmental

Use of blockstone as a low carbon footprint alternative to concrete

Partnering

Early Contractor Involvement

Partnering

Extremely high tidal range and fast flowing river environment

Archaeology

Worked successfully with archaeologists to uncover and document archeologically important historic Roman Bridge at Isca Road

Project Successes

Scheme was extremely popular with local community
Both contracts were completed a month in front of programme

Supply Chain

Unusual engineering techniques

Involvement of other consultants etc

Client Environment Agency
Contact: Tim Hopkins
Value Award Isca Road £ 2m
Award Ebbw Slip £ 0.5m
Role Principal Sub-Contractor
Principal Designer Environment Agency
Principal Contractor Carillion
Form of Contract NEC Option C
Contract Period Isca Road
July 2004 for 40 weeks
Ebbw Slip
Jan 2004 for 13 weeks